PowerSleeve external cladding | Wood Group PSN/Shell
Information
Client
Wood Group PSN
Region
Europe
Industry
Associated capabilities
Challenge
Stork was contracted by Wood Group PSN to reinforce the structural integrity of a two level module after severe corrosion was identified on Shell U.K.’s Brent Alpha installation. All four sides of the module showed severe corrosion and multiple through wall anomalies.
Solution
Stork applied its innovative pipe repair system; PowerSleeve. PowerSleeve’s engineered composite reinforcement was selected because of its 100% solids epoxy impermeable barrier. This combined with the strength of its custom E-glass and Kevlar® fabric made it the best choice to encapsulate and reinforce structures on this project. The surface of the module was hand prepared by Stork’s multi-skilled rope access technicians and all voids filled with epoxy putty to smooth the surface area. All repair calculations are conducted in-house, providing the client with a fully customised rapid delivery.
Benefits
Stork’s technicians were able to completely cover affected area; restoring original structural integrity. Additional workscopes have been requested due to proven results on this workscope.
“Stork’s PowerSleeve delivered a rapid solution which has produced significant time and cost savings. The original structural integrity was completely restored and affected area covered. We found the attitude of the Stork technicians to be of an excellent standard. They displayed a safe and conscientious attitude towards the tasks they were asked to carry out and completed the scope as per the planned timeline.” George Rennie, ISC Fabric Maintenance Lead Wood Group PSN
Project details
Location: Shell U.K., Brent Alpha
When: February 2013
Insulation conditions: 5 C ambient temperatures
Installation type/products: Field wetted Powersleeve composite system
Materials: 5/20UW Eproxy Putty Stick, Power Sleeve® W-11 ® hybrid fabric with Standard Resin, BioDur 563® Epoxy basecoat/ primer and final topcoat
Safety: Project delivered safely with no lost time incidents
Workscope completion: The workscope was completed on time and within budget